if 40 men can finish a job in 12 days how many men should be employed to finish the job in 8 days
Answers
Answered by
3
40 men can finish the job in 12 days
1 man can finish the job in (40×12) days
Let the men finish the job in 8 days be 'S'
'S' men can finish the job in 8x
Answered by
2
Answer:
The number of men required to finish the job in 8 days is 60.
Step-by-step explanation:
Given, 40 men are required to finish the job in 12 days
Number of men required to finish the job in 1 day = ...(1)
For the second case,
Let men required to finish the job in 8 days
Number of men required to finish the job in 1 day = ...(2)
As the work is same, equating both cases for the men required in 1 day,
Therefore, the number of men required to finish the job in 8 days is 60.