Math, asked by varunt802, 1 year ago

if 8 persons can weave 160 shawls in 5 days how many shawls will be woven by 3 persons in 14 days

Answers

Answered by shivamsingh1460
4
Shawls are woven in 1 day by 8 person = 160/8=20
Shawls were woven in 1 day by 1 men =20÷8=2.5
Hence
3 person will be Wave shawls = 2.5 *3=7.5Shawls
Shawl's woven by 3 person in 14 days =14 ×7.5 =105 shawls

Therefore. 105 shawls were woven by 3 person in 14 days

I hope it is helpful for you

varunt802: i got the answer and your answer is wrong its 168 shawls
Answered by pranavjoshuapj
0

Answer:

anser is 168 shawls

Step-by-step explanation: