If Rohit does 60% work in 30 days, in how many days will he finish the work?
Answers
Answered by
2
No. of days Rohit takes to do 60% work = 30
No. of days he takes to do 1% work = 30/60 = ½
No. of days he takes to do 100% work = ½ × 100 = 50
Answer : He will finish the work in 50 days .