If the expected time along the critical path of a project is 27 weeks and the standard deviation along it is 6 weeks, the probability of completing the project within 21 weeks is
Answers
Answered by
0
Answer:
In PERT, the three time estimates are used to find the expected time to ... CP represents activity on critical path: 1. .... (c) Find the probability of completing the project in 32 weeks
Answered by
0
Answer:
The probability of completing the project within 21 weeks is 15.87%
Step-by-step explanation:
- Critical path is the longest path of the project activities. The delay in any activity in critical path can delay the project.
- The given question is solved by the use of standard normal distribution.
- Expected time of the project is 27 weeks.
- The project completition time is 21 weeks.
- The standard deviation of the path is 6 weeks .
- The value of the z used in normal distribution is given by
- At z =-1, the probability from the standard normal curve is 15.87%