Math, asked by naeemabbas5332, 9 months ago

If the expected time along the critical path of a project is 27 weeks and the standard deviation along it is 6 weeks, the probability of completing the project within 21 weeks is

Answers

Answered by Anonymous
0

Answer:

In PERT, the three time estimates are used to find the expected time to ... CP represents activity on critical path: 1. .... (c) Find the probability of completing the project in 32 weeks

Answered by RiteshChandel01
0

Answer:

The probability of completing the project within 21 weeks is 15.87%

Step-by-step explanation:

  • Critical path is the longest path of the project activities. The delay in any activity in critical path can delay the project.
  • The given question is solved by the use of standard normal distribution.
  • Expected time of the project is 27 weeks.
  • The project completition time is 21 weeks.
  • The standard deviation of the path is 6 weeks .
  • The value of the z used in normal distribution is given by

       z=\frac{x-mean}{\sigma}

       z=\frac{21-27}{6}\\z=-1

  • At z =-1, the probability from the standard normal curve is 15.87%