if the net present value of a project is zero based on a discount rate of 20%, then the interanl rate of return is:

Answers

Answered by pareekabhimanyu33
1

Answer:

20%

Explanation:

The discount rate using which the Net Present Value is equal to Nil is equivalent to IRR of the project