If wages of 12 men for 30 days is 4200 what is the wage for 24 men for 18 days
Answers
Answered by
18
Answer:
5040
Step-by-step explanation:
wage of 12 men for 30 days = 4200
wage of 12 men for 1 day = 4200/30
=140
wage of 24 men for 1 day = 140×2=280
wage of 24 men for 18 days = 280×18 =5040