In a construction work a contractor has to pay penalty for delay beyond a certain date - rs 200 for
Answers
Answered by
1
Explanation:
A contract on a construction job specifies a penalty for delay of completion beyond a certain date as follow: Rs.200 for 1st day, Rs.250 for second day, Rs.300 for third day, and so on. If the contractor pays Rs.27750 as penalty, find the number of days for which the construction work was delayed.
Answered by
0
Principle of Availability - An organization shall maintain records in a manner that ensures timely, efficient, and accurate retrieval of needed information. ... The Principles were vetted through a public call-for-comment process involving the professional records information management (RIM) community.