in how many days of working 8hours each day can 12 men do the same work as 10 working 9 hours a day do in 16 days

Answers

Answered by ExoticExplorer
98

Assume that the number of days required be x.

Now, the work done by 10 men in 16 days working 9 hours per day would be equal to the work done by 12 men in days working 8 hours per day.

12*8*x = 10*16*9You will get the value of x = 15.

So they will need 15 days to complete the same amount of work.

Hope this Helps :)