in how many days of working 8hours each day can 12 men do the same work as 10 working 9 hours a day do in 16 days
Answers
Answered by
98
Assume that the number of days required be x.
Now, the work done by 10 men in 16 days working 9 hours per day would be equal to the work done by 12 men in x days working 8 hours per day.
12*8*x = 10*16*9You will get the value of x = 15.So they will need 15 days to complete the same amount of work.
Hope this Helps :)
Answered by
107
Hope it helps you mark me the brainiest
Attachments:
Similar questions
English,
8 months ago
Math,
8 months ago
Chemistry,
8 months ago
Social Sciences,
1 year ago
Social Sciences,
1 year ago