In the middle of the iteration how does a team handle the requirement changes in the customer
Answers
Answered by
0
A Change in the middle of iteration will be accepted within the same sprint only if the following conditions are satisfied: The change has been a confirmed changed with the customer. The change stands well with the value related to the proposition of a story well sprinted.
The change is small. The change has been identified at least 2-3 days prior to the end of the sprint.For all other changes, new stories must be added and to be considered in the current or a subsequent sprint.