it takes 16 hours for three brick layers to build a wall .calculate how long it would take for eight brick layers to build a similar way
Answers
Answered by
9
It takes 16 hours for bricklayers to build a wall.
That means a total of 16 * 3 = 48 man hours are needed.
So when there are eight bricklayers working, the duration it will take to complete the wall is 48 / 8 = 6 hours.
That means a total of 16 * 3 = 48 man hours are needed.
So when there are eight bricklayers working, the duration it will take to complete the wall is 48 / 8 = 6 hours.
kvnmurty:
:-)
Answered by
0
Answer: 6 hrs
Step-by-step explanation:
48/8=6 bhrs