it takes 36 machines to complete a job in 45 days then how many machines are required to complete the same job in 60 days
Answers
Answered by
0
Here is ur answer
Mark as brainliest
Mark as brainliest
Attachments:
Answered by
2
27 machines are required to complete the same job in 60 days.
Step-by-step explanation:
It takes 36 machines to complete a job in 45 days.
Machine = = 36
Days = = 45
Number of machines required to complete the same job in 60 days.
Machines =
Days = = 60
Now,
=> 36 x 45 = x 60
=> = = 27
Hence, 27 machines are required to complete the same job in 60 days.