it takes 36 machines to complete a job in 45 days then how many machines are required to complete the same job in 60 days
Answers
Answered by
0
Here is ur answer
Mark as brainliest
Mark as brainliest
Attachments:
![](https://hi-static.z-dn.net/files/d5b/85a57d8409ff6ba645c4e1d0bc44e088.png)
Answered by
2
27 machines are required to complete the same job in 60 days.
Step-by-step explanation:
It takes 36 machines to complete a job in 45 days.
Machine = = 36
Days = = 45
Number of machines required to complete the same job in 60 days.
Machines =
Days = = 60
Now,
=> 36 x 45 = x 60
=> =
= 27
Hence, 27 machines are required to complete the same job in 60 days.