Let us consider, to deliver car on time three items are
on shortage that is engine, gear box and chassis
Probability of getting engine on time is 0.8 , probability
of getting gear box on time is 0.9 and probability of
getting chassis on time is 0.7. What is the probability
car will be delivered on time?