Math, asked by shreyash7718, 10 months ago

Masons A and B take 12 hours to build a stage together. B and C take 15 hours while A and C take 20 hours to do the same job. How long will it take to build the stage if A, B and C worked together? If ₹1200 is received for building the stage, how will the money be shared among A, B, and C?

Answers

Answered by jack230893
6

Answer:

6:4:2................

Similar questions