number of days from 29th January 2013 to 15 April 2013
Answers
Answered by
8
Hey mate your answer
Number of days from 29th January 2013 to 15 April 2013 is 76
master43:
answer is 78 at the back of book
Answered by
5
Number of days from 29th January 2013 to 15 April 2013 is 76 days.
Step-by-step explanation:
To find : The number of days from 29th January 2013 to 15 April 2013 ?
Solution :
We know that, In 2013
January is 30 days month.
February is 28 days month.
March is 31 days month.
April is 30 day month.
Number of days from 29th January 2013 to 31 January 2013 = 3 days.
Number of days in February month = 28 days.
Number of days in March month = 31 days.
Number of days from 1 April 2013 to 15 April 2013 = 14 days.
Total number of days = 3+28+31+15=76 days
Therefore, number of days from 29th January 2013 to 15 April 2013 is 76 days.