Math, asked by master43, 1 year ago

number of days from 29th January 2013 to 15 April 2013

Answers

Answered by Anonymous
8

Hey mate your answer


Number of days from 29th January 2013 to 15 April 2013 is 76


master43: answer is 78 at the back of book
Anonymous: Probabily but my answer is 76... After checking twice
Answered by pinquancaro
5

Number of days from 29th January 2013 to 15 April 2013 is 76 days.

Step-by-step explanation:

To find : The number of days from 29th January 2013 to 15 April 2013 ?

Solution :

We know that, In 2013

January is 30 days month.

February is 28 days month.

March is 31 days month.

April is 30 day month.

Number of days from 29th January 2013 to 31 January 2013 = 3 days.

Number of days in February month = 28 days.

Number of days in March month = 31 days.

Number of days from 1 April 2013 to 15 April  2013 = 14 days.

Total number of days = 3+28+31+15=76 days

Therefore, number of days from 29th January 2013 to 15 April 2013 is 76 days.