person a can complete a job in 48 minutes while B can complete the same job in 60 minutes how long will they take to complete the job together
Answers
Answered by
6
A can complete a work in 48minutes
In 1 minute A can do 1/48 of work
Similarly in 1 minute B can do 1/60 of work
Together in 1 minute they would do
simplifying 9/240 we get
9/240
= 3/80
In 1 minute A and B together can do 3/80 of work
So whole work they can do in 1 ÷ 3/80
= 1 × 80/3
= 80/3 minutes
= 26.67 minutes
So they can finish the work in 80/3 or 26.67 minutes
In 1 minute A can do 1/48 of work
Similarly in 1 minute B can do 1/60 of work
Together in 1 minute they would do
simplifying 9/240 we get
9/240
= 3/80
In 1 minute A and B together can do 3/80 of work
So whole work they can do in 1 ÷ 3/80
= 1 × 80/3
= 80/3 minutes
= 26.67 minutes
So they can finish the work in 80/3 or 26.67 minutes