Math, asked by tom68, 1 year ago

pintu takes 6 days more than those of Nishu to complete certain work. lf they work together they finish it in 4 days. how many days would it take to complete the work if they work alone

Answers

Answered by shuklashit
4
(x+x+6)/2=4
=>2x+6 = 4×2
=>2x = 8-6
=>x =2/2
=>x = 1
therefore it would take 1+1+6=8days to complete the work if they work alone.