Math, asked by mouni610, 1 year ago

plz.. answer 9th sum

Attachments:

Answers

Answered by barath93
1

2/3 is the correct answer


mouni610: how can we do this
Answered by avinasg
4

1 person is x 6day

2 is y 8 day

3 is z 12 day

Work done by all three in one day is x =1/6 y=1/8 z=1/12 respectively

If they work together work done in one day = 1/6 +1/8 +1/12

=9/24

Work done in 1 day is 9/24

Total time 24/9 =2²/³


IshitaJaiswal: Great Answer.
barath93: yeah
avinasg: thanks
IshitaJaiswal: my pleasure @avinasg
IshitaJaiswal: thanks for a FollowBack.
avinasg: thanks for following me
IshitaJaiswal: ^_^