Math, asked by Aanvigahoi, 1 year ago

plzzz help...

if 24 men can lay a road of length 15km in 18days, in how many days will 21men lay a road 35km long?

Answers

Answered by Thatsomeone
4
This question is of inverse proportion

so product remains constant

let required days be x

24 × 15 × 18 = constant

21 × 35 × x = constant

so

24 × 15 × 18 = 21 × 35 × x

x = 24 × 15 × 18 /21 × 35

x = 8 × 3 × 18 / 7 × 7

x = 8 ( approximately )