procedure of fabrication used in civil construction​

Answers

Answered by manna29
0

Explanation:

Fabrication Processes

Mill material is cut to length by sawing, shearing, or flame cutting. Columns may also be milled to their final length. Holes for fasteners are drilled or punched. Punched and reamed holes are seldom used in building construction.

Answered by yokavya0008
0

Explanation:

Structural steel fabrication can be carried out in shop or at the construction site.  

Fabrication of steelwork carried out in shops is precise and of assured quality, whereas

field fabrication is comparatively of inferior in quality. In India construction site

fabrication is most common even in large projects due to inexpensive field labour, high

cost of transportation, difficulty in the transportation of large members, higher excise

duty on products from shop. Beneficial taxation for site work is a major financial

incentive for site fabrication. The methods followed in site fabrication are similar but the

level of sophistication of equipment at site and environmental control would be usually

less. The skill of personnel at site also tends to be inferior and hence the quality of

finished product tends to be relatively inferior. However, shop fabrication is efficient in

terms of cost, time and quality.

Structural steel passes through various operations during the course of its fabrication.  

Generally, the sequence of activities in fabricating shops is as shown in Table1. The

sequence and importance of shop operations will vary depending on the type of

fabrication required. All these activities are explained briefly in the subsequent parts of

the section