QUESTION 2 OF 20.
Solve the following problem and select the best of the answer choices given,
A can complete a work in 20 days, B can complete the same work in 30 days. If they decided to work on alternate days, if
how many days will the work be completed?
24 days
Cannot be determined
12 days
20 days
Resel Answer
Prev
Mark For Review
How
Nest
* Negative marks apply for wrong answer​

Answers

Answered by TKM13
0

Answer:

the work will be completed in 12 days

Step-by-step explanation:

20-30= 10

24 1/2 =12