Raju can do a piece of work in 10 days, Vicky in 12 days and Tinku in 15 days. They all start
the work together, but Raju leaves after 2 days and Vicky leaves 3 days before the work is completed. In how many days is the work completed?
(1) 5 days
(2) 16 days
(3) 7 days
(4) 8 days
Answers
Step by step solution
________________
One day's work of Raju = 1/0
" " " " Vicky = 1/12
" " " " Tinku = 1/15
2 day's work of all = 2 x ( 1/10 + 1/12 + 1/15 ) ------------------- ( 2 days)
= 2x 15/60
= 1/2
Remaining work = 1 - 1/2 = 1/2
Last 3 day's work is done by Tinku alone as Vicky leaves 3 days before the work is completed.
So, Tinku's 3 day's work = 3 x 1/15 = 1/5 ....................................... ( 3 days)
Total work done so far, 1/2 + 1/5 = 7/10
Remaining work = 1 - 7/10 = 3/10
This 3/10 work is done by both, Vicky and Tinku
one day's work of Vicky and Tinku = 1/12 + 1/15 = 9/60 = 3/20
Now , we will use Unitary Method to find the number of days taken by Vicky and Tinku to complete the remaining 3/10 of work.
Vicky + Tinku complete 3/20 part in = 1 day
" " " 1 part = 1 x 3/20
" " " 3/10 part = 3/20 ÷ 3/10
= 3/20 x 10/3
= 1/2
So, Vicky + Tinku complete 3/10 remaining part in 2 days ................( 2 days)
Total days taken to complete the work are 2 + 3 + 2 + = 7 days.
so, the required answer is 7 days.
◼◼◼
_____________________________________________
Any problem in understanding the solution , please free to ask in the comment box.