Math, asked by tomystalin, 11 months ago

Raksha can complete a piece of work
in 27 days while Esther takes 45 days
to complete the work. They start
working together, but Raksha leaves
9 days before the work gets over. For
how many days does Esther work?​

Answers

Answered by cherrybabbly
1

Answer:

15

Step-by-step explanation:

Raksha =27 days=9

Esther=45 days =x

27x=9*45

27x= 405

x=405/27

x=15

Esther takes 15 days

Answered by slicergiza
7

Esther worked for 22.5 days.

Step-by-step explanation:

Given,

Raksha can complete a piece of work  in 27 days,

So, the one day work of Raksha = \frac{1}{27},

Similarly, Esther takes 45 days  to complete the work,

The one day work of Esther = \frac{1}{45}

Total one day work = \frac{1}{27}+\frac{1}{45}

=\frac{5+3}{135}

=\frac{8}{135}

Consider the work is completed in x days,

Since, for 9 days before completion of work they work together,

That is, total work for (x-9) days = Number of days she worked × One day work,

= (x-9)\times \frac{8}{135}

Now, remaining part of work is completed by Esther alone in 9 days,

So, remaining part of work = 9\times \frac{1}{45}=\frac{1}{5}

∵ Total part = 1

\implies (x-9)\times \frac{8}{135} + \frac{1}{5}=1

\frac{8x-72}{135}+\frac{27}{135}=1

8x-72+27=135

8x - 45 = 135

8x = 180

\implies x =\frac{180}{8}=22.5

Hence, Esther worked for 22.5 days.