Ramesh can complete a piece of work in 25 days. mahesh, who is 50% more efficient joins ramesh to do this work. how many days will they take together to complete?

Answers

Answered by gautam96
1
12 days time will take to complete the work
Answered by Anonymous
0
they will take together to complete in 12 days.