SS Company manufacturing electronic equipment purchase
transistors @30 per unit the annual requirement of transistors is 5000
units. The ordering cost is 200 per order. Carrying cost is 4/- per unit,
lead time is 5 days calculate EOQ and reorder point?
Answers
Answered by
2
Answer:
EOQ = 707.10
Step-by-step explanation:
EOQ stands for Economic Ordering Quantity. It can be mathematically written as
= SQRT ((2 X Annual consumption X Cost per order) / (Holding cost))
As per given information,
Annual consumption = 5000
Cost per order = 200
Holding Cost = 4
Putting the values in the above equation we have;
EOQ = SQRT (2 X5000 X200 / (4))
EOQ = SQRT (500000)
EOQ = 707.10