Accountancy, asked by shubhneetoshan4697, 10 months ago

Standard cost of product is :Time : 6 hours per unitRate : Rs 4 per hourActual cost :Production 1,500 unitsHours taken 7,600 unitsIdle time (in hours) 400Total hours : 8,000Total labour cost announced to Rs. 40,000. Calculate Labour Variance.​

Answers

Answered by anamkhurshid29
1

Standard cost of product is :Time : 6 hours per unitRate : Rs 4 per hourActual cost :Production

Hope this helps ❤️❤️