Standard cost of product is :Time : 6 hours per unitRate : Rs 4 per hourActual cost :Production 1,500 unitsHours taken 7,600 unitsIdle time (in hours) 400Total hours : 8,000Total labour cost announced to Rs. 40,000. Calculate Labour Variance.
Answers
Answered by
1
Standard cost of product is :Time : 6 hours per unitRate : Rs 4 per hourActual cost :Production
Hope this helps ❤️❤️