Business Studies, asked by kanikachaudary5604, 11 months ago

The second step in the project control process for measuring and evaluating project performance is to

a.Review the baseline plan with top management

b.Analyze inputs to control system

c.Compare plan against actual

d.Measure progress and performance

e.Review spending with team members

Answers

Answered by spiderman2019
0

Answer:

D) Measure progress and performance

Explanation:

Answered by chaudhary532
0

Answer:

your ans

Explanation:

ans is d . measure progress and performance