The second step in the project control process for measuring and evaluating project performance is to
a.Review the baseline plan with top management
b.Analyze inputs to control system
c.Compare plan against actual
d.Measure progress and performance
e.Review spending with team members
Answers
Answered by
0
Answer:
D) Measure progress and performance
Explanation:
Answered by
0
Answer:
your ans
Explanation:
ans is d . measure progress and performance