Math, asked by Shameermd111, 3 months ago

12 member can do an embroidery work in 24 days, then the number of women required to complete the same work 18 day's is


1 . 15

2. 16

3. 18

4. 10​

Answers

Answered by shrutipaul2006
2

Answer:

Answere is 10 cause 9 women are required to complete the work within 18 days but there's no option of 9 ...so Maybe it's 10