12 worker can do a piece of work in 20 days.How many workers should be added to complete the work in 16 days?
Answers
Answered by
3
Answer:
since, it is a case of indirect variation.
Let the no of workers be x
According to questions,
6×12=x×16
x=12×20/16
x=15
Total no of workers needed to complete the same work in 19 days=15.
Hey, this is the answer.
Please mark me as brainliest.
Answered by
0
Answer:
15 worders needed
Step-by-step explanation: