Math, asked by Laly7465, 1 year ago

20 men can complete the work in 48 days .8 days after they started the work 12 more men joined them.in how many days the whole work wiil be comlete.

Answers

Answered by desiboyz3
0
5 days will be the answer
Attachments:
Answered by TooFree
0

20 men can complete the work in 48 days.

⇒ Total man-days needed for the project = 20 x 48 = 960


8 days of work = 8 x 20 = 160 man-days

⇒ Number of man-days needed to complete the project = 960 - 160 = 800


After 12 more men joined in

⇒ there are 20 + 12 = 32 men


Number of days needed = 800 ÷ 32 = 25 days.


Total number of days needed to complete the job = 8 + 25 = 33 days


Answer: 33 days