6 men can complete the electrical wiringof a housein 7 day. in how manydays 21 men can do this work
Answers
Answered by
0
Answer: 21 men can do the work in 2 days
Step-by-step explanation:
6 men do
6*7 mandays of work = 42 mandays
let the number of days in which 21 men can do be x
then
21*x = 42
x = 42/21
=> x = 2 days