A alone can do a piece of work in 12 days and B alone can do the same work in 15 days. They start working together. After 4 days, B leaves the work. In how many days will A alone complete the remaining work?
Answers
Given :
- A alone can do a piece of work in 12 days
- B alone can do the same work in 15 days
- After 4 days , B leaves the work after working together.
To find :
- In how many days A will alone finish the remaining work
Solution :
At first,
In 12 days, A can do work = 1 part
∴ In 1 day, a can do = 1/12 part of work.
Now,
In 15 days, B can do = 1 part of work
∴ In 1 day, B can do = 1/15 part of work.
So, in 1 day :
A and b together can do = (1/12) + (1/15) part of work
= (5 + 4)/60 part of work
= 9/60 part of work
= 3/20 part of work
So they work together for 4 days, so ;
Total work done by both in 4 days = 4 * (3/20) part of work
= 3/5 part of work
So, work left = (1 - 3/5) part
= (5 - 3)/5 part
= 2/5 parts
So, A alone has to do = 2/5 parts of work.
Now A alone can do 1 part of work in 12 days.
∴ A alone can do 2/5 parts of work in = (12 * 2/5) days
= 24/5 days
= 4.8 days
Therefore,
In 4.8 days , A alone will complete the remaining work.
Answer :-
Here the concept of Work and Day relationship has been used. We know that number of days taken to complete a work is equal to the fraction of number of day and day taken, which represents the work in one day.
____________________________________
★ Question :-
A alone can do a piece of work in 12 days and B alone can do the same work in 15 days. They start working together. After 4 days, B leaves the work. In how many days will A alone complete the remaining work?
____________________________________
★ Solution :-
Given,
» A alone can do a piece of work in 12 days
» B alone can do the same work in 15 days
Then,
So, now according to the question,
A and B start working together so,
➔ Work done by A and B = (1/12) + (1/15)
➔ Work done by A and B = (4 + 5) / 60
➔ Work done by A and B = 9/60
➔ Work done by A and B = 3/20
• So, workdone by A and B, in 4 days :-
⟹ Hence, work done by A and B in four days = 3/5
Now remaining work, is given as :-
Then, we know that A completes the work in 12 days. So using Unitary Method, we get,
➠ No. of days taken by A to complete the work = 2 × 2.4 = 4.8
_______________________________
• Time is the standard measure of the change in phases of the day.
• No. of days to day a work, is derived from the relation where work done in one day = reciprocal of number of days required to do the work.