A work which could be finished in 9 days was finished 3 days earlier after 10 more men joined. the number of men employed was?
Answers
Answered by
16
20 no of employee... please mark it as a brainliest answer
Attachments:
Answered by
10
Answer:
20
Step-by-step explanation:
Let x be the initial no. of men
x men can complete work in days = 9
1 man can complete work in days = 9x
10 more man joined
So, x+10 men can complete work in days =
We are given that when 10 more men joined then work was finished 3 days earlier i.e. 9-3 = 6 days
So,
Hence the number of men employed was 20