Chiraji can do a work in 15days ,natthi 25days and sumera in 30 days.how long will they take to do the work if they work togethher?
Answers
Answered by
2
Work done by Chiraji in one day = 1/15
Work done by Natthi in one day = 1/25
Work done by Sameera in one day = 1/30
Work done by these three in one day
= 1/15 + 1/25 + 1/30
= 10 + 6 + 5 / 150
= 21 / 150
So time taken by these three to comokete work
= 150 / 21
Work done by Natthi in one day = 1/25
Work done by Sameera in one day = 1/30
Work done by these three in one day
= 1/15 + 1/25 + 1/30
= 10 + 6 + 5 / 150
= 21 / 150
So time taken by these three to comokete work
= 150 / 21
Similar questions
English,
7 months ago
Accountancy,
7 months ago
Math,
1 year ago
Math,
1 year ago
English,
1 year ago