If 8 workers can complete a work in 24 days, then 24 workers can complete the same work in how many days.
Answer with steps

Answers

Answered by MRsooN
1
use the Formula

workers * days = work

SO
8 * 24 * w2 = 24 * x * w1
as w1 and w2 are same they got cancelled
8 * 24 / 24 = 8 days is the answer