If two men and 3 women take 40 hours to do a certain piece of work, how long will 4 men and 9 women working together take to complete the work?
Answers
Answered by
1
Answer:
Step-by-step explanation:
2 men------3women------40 hrs
4 men------9women------?
2/4 *9/3 *40 =60 hrs