A and b can work in 9 days, a alone can finish work in 12days. in how many days can b alone can complete work
Answers
Answered by
1
3 day in complete the work B
Answered by
2
Heya friend,
One day work of A & B=1/9
One day work of A = 1/12
One day work of B= 1/9 - 1/12
=1/36
Work done by B = 36 days
Hope this helps you
One day work of A & B=1/9
One day work of A = 1/12
One day work of B= 1/9 - 1/12
=1/36
Work done by B = 36 days
Hope this helps you